Tres Puentes

New Construction of 2 new buildings on either side of an existing Low-Income Housing Building, a 175-unit Low Income Building and a 119-unit Low Income Senior Citizen Building
Deep pile foundation system.  Steel and concrete support structure
KOW was retained during the final design stages of the pre-construction phase.  The contractor was in place and we were brought in at a time where we could provide assessment of the final coordination and contracts prior to construction commencement.   KOW works closely in conjunction with WSFSSH development staff to bolster their team with our technical knowledge and process understanding.
Original Budget – $73,697,000 / Current Budget – $76,807,00

Client

Tres Puentes, 285 East 185th Street, Bronx, NY

Our Role

Owner's Representative